SoPo Sk8 Park Overview 1.jpg

 

1.jpg

 Progress as of November 17, 2023. 

Update 11.17.23

Construction is moving along and is anticipated to be complete by mid-December, 2022. A grand opening will take place in the spring of 2023, date/time TBA. 

  • Park Location: 230 Evan St, South Portland, otherwise known as High School Park.
  • Bid for construction: Awarded to American Ramp Company. Pillar Design Studios (skatepark designer) has been hired as construction administration to oversee the project. 
  • Construction Plans
  • Construction schedule: began September 12, 2022. Anticipated to be complete by mid December, 2022 (weather permitting).  
  • Skate Jam Fundraiser held on August 29, 2021 

Questions regarding the skatepark project can be directed to Anthony Johnson at 767-7650 ext 7512 or ajohnson@southportland.org 

 

SPONSORS  

WE ARE HAPPY TO ANNOUNCE THAT OUR FUNDRAISING EFFORTS HAVE BEEN COMPLETED.  

HUGE THANKS to all of our sponsors and individual donors! This project would not be possible without you. 

 Annenberg_Foundation_Logo.jpg

THE LONG FAMILY

 

Libra Foundation logo.png

Saco Biddeford Savings Logo.png

 

 

 jwLogoBoxedName.png

 Bangor Savings logo.png

 TownCountryFCU_Logo_RGB.png